In September 2017 we began the £1m project at Upper Shirley High School.

Temporary classrooms have been installed and the existing classrooms demolished to make way for the new 2 storey block of 6 classrooms and offices.

The foundations and ground floor slab have been completed, the superstructure masonry is now in progress and is nearing ground floor window lintel level.
We are delighted to say we are on target for our July completion!.