Wildern School - Re-Roofing & Replacement Curtain Walling

Project Description :
Re-Roofing & Replacement Curtain Walling to Blocks 3 & 6

Client :
Governors of Wildern School

Location :
Hedge End, Hampshire

Architect :
Avenues Ltd

Quantity Surveyors :
KSP Consultancy LLP

Contract Value :
£634k

Procurement/contract :
Traditional Tender
JCT Intermediate Building Contract 2011 Edition

Contract Period :
15 Weeks

Discuss Your Project with Our Team

Project Key Features: 

  • Asbestos removal
  • Removal of existing and Installation of new curtain walling
  • Installation of new Bauder 20 year guarantee flat roof system
  • Single ply pitched roofing
  • Replacement roof lights
  • Installation of 6 Monodraught X-Air 170 Natural ventilation units and structural works in Association
  • New rainwater installation
  • Replacement ceiling
  • Replacement LED lighting
  • Internal decorations
  • Associated electrical & mechanical works